|






| |
 |
Asian Counseling Building
The
project is a building that has three stories above ground with two stories below
ground. The site is an area of old, loosely-placed fill with debris.
Significant ground water was encountered within the fill. Soils underlying
fills were easily disturbed silts. Cornerstone provided design
consultation and construction observation.
|
| |
|
Salmon Bay Marina
This
renovation of a previous shipyard and repair facility includes both onshore
office and warehouse structures in addition to floating docks. The office
structures required installation of 18-inch-diameter auger cast piles. The
floating docks are anchored in place using up to 20-inch-diameter steel pipe
piles.
|
 |
 |
| |
|
|
Rattlesnake Mountain Communications Tower
Located
near the summit of Rattlesnake Mountain in Snoqualmie, this three-legged,
275-foot-tall, steel-lattice communications tower was initially planned to be
founded on three 8-foot-diameter drilled shafts, which were to extend 50 feet
into the underlying highly-weathered bedrock. We explored the subsurface
conditions by drilling three borings to depths of up to 44 feet and then
conducted a vertical capacity analysis and provided capacities for various-sized
drilled shafts. Our analysis and resulting recommendations enabled the
tower to be founded on substantially less expensive, 6-foot-diameter,
37-foot-deep drilled shafts. We also observed and documented the
installation of the drilled shafts.
|
 |
 |
Perrigo Park
Cornerstone
Geotechnical was retained near the end of the project to complete groundwater
mounding analysis of the on-site stormwater infiltration system.
This work was completed to satisfy the King County stormwater design criteria
for infiltration systems.
|
|
Cingular Building
As part of
an upgrade to disaster preparedness, the Cingular Company installed an addition
to one of their buildings to house new generators. The building is located
in the North Creek area of Bothell. They also installed an
additional 40,000 gallon underground fuel storage tank. The project site
was underlain by 12 to 20 feet of peat, requiring the use of auger cast piling.
The tank excavation required steel sheet piling and dewatering wells.
|
 |
 |
Foundation House
Geotechnical consultation and construction observation
at a senior-living center in Bothell. The site access road had an
alignment along a slope and crossed a known deep-seated landslide in
low-strength silt soils. We prepared a design to improve the stability of
the slope above and below the access road using soil-cement filled trenches.
|
Homewood Suites Hotel
Located in Seattle, the project included the construction of a 26-foot-high
soldier pile wall with tiebacks allowing excavation cuts to the property lines.
A portion of this shoring wall also acted as underpinning for adjacent building.
We provided drilled-pier design recommendations, in addition to construction
observation and consultation services during construction.
|
 |
 |
Garden Grove
Garden Grove is a mixed-use commercial development consisting of a senior-living center, office buildings, and a large self-storage facility. Subsurface
conditions at the site included old fill, silts, glacial till, and buried
topsoil. A combination of overexcavation and the installation of concrete piers
solved the variety of problems posed by the subsurface conditions.
|
University Child Development School
We conducted a soil investigation and provided construction observation
services for the school’s new building and playground. The unique architecture
and the terrain of the site made foundation construction very challenging.
Cornerstone Geotechnical, Inc. was named as “special inspectors” for the project
and made economical consultation recommendations regarding the use of on-site
soils.
|
 |
 |
Campbell’s Soup
Landslide Repair
This
project involved the repair of a deep-seated landslide behind the Campbell’s
Soup facility along Highway 9 that threatened BNSF railroad tracks. The
challenges posed by this site included artesian conditions below the slide.
Using back calculations from field measurements, we established soil parameters
to aid our design of large-diameter concrete piers to support the
landslide mass. We also provided construction observation services and installed
instrumentation to monitor future slope movement.
|
Shoring for Mixed-Use Building
This three-story mixed-use building in Edmonds needed a 12 foot cut for an
underground parking garage. The proximity of the excavation to neighboring
structures required the use of temporary shoring during construction. During the
installation of the soldier pile shoring wall, we evaluated soil and groundwater
conditions encountered and provided recommendations for drainage.
|
 |
Woodland Meadows
This residential development in
Bothell, built primarily on a hillside, located three homes over a pre-existing
filled pond. We mapped subsurface peat deposits as deep as 18 feet. These houses
were founded on deep auger-cast piers embedded in the dense material underlying
the peat. We provided depth recommendations and construction observation
services for the pier installation.
|
 |
| |
|